example:Question number: 128
What is the order of the Procurement Management processes?
A) Plan Purchases and Acquisitions, Plan Contracting, Request Seller Responses, Select
Sellers, Contract Administration, Contract Closure
B) Plan Purchases and Acquisitions, Plan Contracting, Select Sellers, Request Seller
Responses, Contract Administration, Contract Closure
C) Plan Purchases and Acquisitions, Plan Contracting, Contract Administration, Request
Seller Responses, Select Sellers, Contract Closure
D) Plan Contracting, Plan Purchases and Acquisitions, Request Seller Responses, Select
Sellers, Contract Administration, Contract Closure
4th Edition process are: Plan Procurements; Conduct Procurements; Administer Procurements; Close Procurements